Full EPC contractor for plant at Ketura and plant at Zmorot, for EDF and Arava Power, including:
- Feasibility study
- High level and detailed design
- All civil works, drainage system and earthworks
- All electrical works – AC, DC, MV
- All VLV works – SCADA, security, communications, cyber security
- Connection to 161KV substation
- Interfacing with grid owner
- O&M for 20 years
Year of construction: 2014-2015